The Allahabad High Court has held that a bidder does not acquire an enforceable right to a government contract merely by becoming the lowest eligible bidder. The Court observed that the government can cancel a tender in public interest when no bidder agrees to execute the work at the rate considered financially appropriate by the authorities.
A Division Bench of the Allahabad High Court, comprising Justice Prakash Padia and Justice Indrajeet Shukla, delivered the ruling while deciding a writ petition filed by M/s Shiv Anant Enterprises against the State of Uttar Pradesh and others.
The firm had challenged the cancellation of a tender for transportation of food grains in Block Bansi, District Siddharth Nagar, along with the department's decision to invite fresh bids.
Background
The dispute arose after three contractors participated in the tender process. M/s Hamara Pump Itwa Fuel Centre was initially declared L-1 (lowest bidder), while Shiv Anant Enterprises was placed at L-2.
However, Hamara Pump's technical bid was subsequently found non-responsive because the vehicle it offered was a tanker registered for transporting petroleum products rather than food grains. Its work order was consequently cancelled.
The department then offered Shiv Anant Enterprises an opportunity to execute the contract at Hamara Pump's quoted rate of 55.010% above the Basic Schedule of Rates (BSR). The firm did not furnish its consent, instead seeking consideration of its own quoted rate. The department subsequently cancelled the tender and invited fresh bids.
Court's Observations
The Bench acknowledged that Hamara Pump's technical bid was defective from the beginning. However, it clarified that even being treated as the highest bidder after the disqualification of another participant did not create an automatic right to receive the contract.
The Court observed:
"The highest bidder has limited rights of equality, fair treatment and negotiation; the bid offered by him cannot be enforced unless the same is translated into a formal contract/agreement."
The Bench also distinguished the present matter from another tender involving Block Nath Nagar, where the L-2 bidder had agreed to execute the work at the negotiated rate.
On the confusion regarding the numbering of cancellation and fresh tender letters, the Court treated it as an inadvertent error and cautioned the authorities to remain careful in future.
Decision
The Court held that the petitioner had no indefeasible right to demand the contract and found no mala fide intention behind the cancellation.
However, during the proceedings, the firm expressed willingness to execute the work at Hamara Pump's quoted rate. The State also agreed to honour this offer.
The Bench permitted the petitioner to submit a fresh representation within one week. It directed the authorities to honour the offer and issue the work order promptly, provided there was no other legal impediment.
The writ petition was accordingly disposed.
Case Title: M/s Shiv Anant Enterprises v. State of U.P. and 3 Others
Case Number: Writ-C No. 40904 of 2026