The Supreme Court has restored an arbitration award in favour of M/s Marino Dredgeco Limited in its dispute with the Board of Trustees of the Port of Kolkata, setting aside a Calcutta High Court judgment that had reduced the contractor's additional work claims by 50%.
A Bench of Justice J.B. Pardiwala and Justice K. Vinod Chandran held that a court exercising jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996, cannot interfere with an arbitral award merely because the amount awarded appears excessive. Such interference must be supported by legally recognised grounds under the Act.
Background
The dispute arose from a contract awarded to Marino Dredgeco Limited for dredging the riverbed and shores at Sagar Island to develop an approach channel and basin for a shore-based pilot station.
The original work was completed and the pilot station was inaugurated on April 17, 2001. However, additional dredging became necessary because of repeated siltation, adverse weather conditions and differences between the actual soil conditions and the data supplied by the Port Trust.
The contractor raised additional bills for the work, leading to arbitration. On November 3, 2003, the arbitrator passed an award quantifying the amounts payable. The Calcutta High Court Single Judge upheld the award under Section 34.
However, a Division Bench subsequently modified it, reducing the payable amount to 50% and lowering the interest rate to 6%, primarily because the additional work claims exceeded 70% of the original contract value.
Examining the dispute, the Supreme Court noted that the additional work involved the same nature of dredging as the original contract. The contractor's claims were supported by measurements, invoices and documents relating to the work performed.
The Court also observed that the absence of a completion certificate could not automatically defeat the contractor's entitlement, particularly when the Port Trust itself had not issued the certificate.
Referring to the principles laid down in Ssangyong Engineering & Construction Co. Ltd. v. NHAI, the Bench emphasised that the expression 'shocking the conscience of the Court' cannot be used without substantive justification.
The judgment observed:
"there should be a substantive reason which blatantly and patently brings forth the conflict with the most basic notions of morality or justice"
The Court further clarified that the Government cannot receive different treatment merely because it is a State entity. Both parties to arbitration must be treated equally, and an award cannot be reduced simply because the amount appears excessive without supporting legal grounds.
Finding that the High Court Division Bench had exceeded the limited scope of interference under Section 37, the Supreme Court set aside the impugned judgment and restored the original arbitral award.
The Court concluded:
"The order impugned is set aside and the appeal of the contractor is allowed. The arbitral award stands restored."
Accordingly, the contractor's appeal was allowed, while the Port Trust's appeal was disposed of.