The Supreme Court has permitted limited payments from the frozen accounts of Parsvnath Developers and its associated companies to prevent disruption of ongoing housing projects and address pending obligations towards homebuyers and employees.
A Bench comprising Chief Justice Surya Kant and Justice Joymalya Bagchi passed the directions on November 5, 2026, while hearing a batch of petitions concerning the builders.
The Court was considering the formation and composition of a committee that could take responsibility for completing projects undertaken by the respondent-builders and their associated companies. The issue remained under consideration.
The Bench observed:
"We have heard learned senior counsel/counsel for the parties at a considerable length on the issue of the nature and composition of the Committee that may be entrusted with the responsibility of completing all the projects of the respondent-builder(s) or their sister concerns and allied and associated companies."
Modifying its earlier account-freezing order dated July 13, 2026, the Court permitted the Resolution Professional (RP) to pay electricity bills, employee dues and expenses for essential facilities such as water supply. Lending financial institutions were directed to provide the necessary funds.
The Bench also directed registration of sale deeds for completed apartments already handed over to verified allottees, provided the project had an occupancy certificate. No third-party rights could be created.
On compensation, the Court clarified:
"Paragraph 4 of the order dated 09.10.2026 is also modified and clarified to the effect that payment of compensation as per the Awards passed by RERA to senior citizens aged 75 and above be considered and expedited."
The matters were listed for further hearing on December 9, 2026.