the Supreme Court of India dismissed a set of civil appeals filed by the Uttar Pradesh Avas Evam Vikas Parishad (Housing Board) and the State of Uttar Pradesh against real estate developer M/s Gaursons India Pvt. Ltd. The court refused to revive a ₹388 crore demand notice that had been raised against the developer for land on which over 2,900 housing units had already been constructed and sold to homebuyers.
Background
The roots of this dispute go back to the 1980s, when the Housing Board notified land for its Vasundhara Scheme in Ghaziabad. Around 12.047 acres belonging to two predecessor companies - later sold to Gaursons India in 2005 - were acquired. Following litigation, a compromise was recorded before the Supreme Court in 1995, under which the Housing Board agreed to adjust the land within the scheme in exchange for no monetary compensation between the parties.
A formal exchange deed was signed in 2004, but it quickly unravelled. The Housing Board had allotted Khasra Nos. 948 and 1454 in Arthala village — land that the District Magistrate had already reserved for a bird sanctuary in 1994, and which the revenue records showed as a “lake” and “banjar” (wasteland). Gaursons India, which had purchased the land from the original owners by then, was left without usable property through no fault of its own.
After years of further litigation, a second exchange deed was executed in 2016, allotting a residential plot in the Siddharth Vihar Yojana. Gaursons paid ₹32.45 crore in conversion charges and went on to build 2,476 general housing units and 450 EWS/LIG flats under the Pradhan Mantri Awas Yojana, with third-party rights created in favour of homebuyers.
The bench of Justice Pamidighantam Sri Narasimha and Justice Alok Aradhe found no merit in the state’s high-pitched arguments. On the core question of whether the 2004 deed’s restrictions travelled into the 2016 deed, the court was unequivocal.
“Since the 2004 Exchange Deed does not survive owing to the Housing Board’s failure to exercise caution in making the alternative allotment, the stipulation in Clause 4 of the Deed would not bind the first respondent.”
The court also rejected the argument that Gaursons had misrepresented facts to obtain the 2016 exchange, noting that the deed itself explicitly described the plot as residential freehold and permitted construction. On the ₹388 crore demand, the court observed that the Housing Board had retained and monetised the original Vasundhara Scheme land — which carried considerably higher circle rates — without paying any compensation, and therefore had no ground to raise a fresh demand.
“The Housing Board has thus retained and developed the acquired land, which is of greater value than the land it gave in exchange, without paying any compensation to the predecessors-in-interest. It cannot, in these circumstances, demand a further price from the first respondent for the substituted land.”
The Supreme Court dismissed all four civil appeals. It affirmed the Allahabad High Court’s February 2023 order setting aside the ₹388 crore demand notice and the direction to allot the land at current bulk sale rates.
On the pending allotment of 450 EWS/LIG flats, the court extended the time available to the state government by three months from the date of its judgment.